Réseau express métropolitain

From Justapedia, unleashing the power of collective wisdom
Jump to navigation Jump to search

Réseau express métropolitain
Réseau express métropolitain logo.png
Overview
OwnerCDPQ Infra
LocaleGreater Montreal
Transit typeLight metro
Number of lines1 (3 branches)
Number of stations26
Daily ridership190,000 (projected)[1]
Websiterem.info/en
Operation
Operation will start2023 (2023) (first section between Brossard and Central Station)
Operator(s)SNC-LavalinAlstom
Number of vehicles212 Alstom Metropolis[2]
Train length2 cars (4 during rush hour)
Technical
System length67 km (42 mi)[3]
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
ElectrificationOverhead line1,500 V DC
Average speed51 km/h (32 mph)
Top speed100 km/h (62 mph)

The Réseau express métropolitain (REM; English: Metropolitan Express Network) is a light metro rapid transit system under construction in Greater Montreal, Quebec, Canada. The system will link several Montreal suburbs, including Montréal–Trudeau International Airport, to Downtown Montreal. The existing Deux-Montagnes line will be converted to light metro standards.

The 67-kilometre (42 mi) light metro rail system is projected to cost $6.9 billion.[4] It will be independent of—but connected to—the existing Montreal Metro, operated by the STM. Trains on the network will be fully automated and driverless, and it will become the fifth-longest automated transportation system in the world, after the Singapore Mass Rapid Transit, Kuala Lumpur Rapid KL, Vancouver SkyTrain, and Dubai Metro.[5]

The first section between Brossard and Central Station is expected to open in the second quarter of 2023.[6]

History

On 13 January 2015, Quebec Premier Philippe Couillard and Michael Sabia, CEO of Caisse de dépôt et placement du Québec (CDPQ), agreed to a partnership in which the Crown corporation could assume financing for major transportation projects in the province, with $7.4 billion planned to be spent on infrastructure from 2014 to 2024.[7] Two of these projects were the South Shore Line and the Train de l'Ouest toward the West Island, which eventually merged to become the core of the REM project.[8]

On 22 April 2016, Sabia and Montreal Mayor Denis Coderre unveiled the project, then known as the Réseau électrique métropolitain, to the media. The estimated completion date for the first portion of the system was December 2020. On 22 June 2016, CDPQ Infra published two requests for qualification: one for the engineering, procurement and construction contract and the other for the rolling stock, systems, operation, and maintenance. The estimated value of the two contracts are $4 billion and $1.5 billion respectively.[9]

On 25 November 2016, CDPQ Infra announced the addition of three new stations to the project. These new stations—Central Station, McGill, and Édouard-Montpetit—would improve downtown Montreal service by integrating the REM with the Metro system through connections to the Orange, Green and Blue Lines. Included with news of the 3 new stations was an increased price tag of $5.9 billion for the entire project.[10][11]

On 15 June 2017, the Government of Canada pledged $1.28 billion to finance the project,[12] completing the financing of the project. Construction on the project was announced as starting at the end of 2017.

On 1 December 2017, the CDPQ extended the tender process on the project to the end of January 2018, citing a need for additional discussions with the bidders.[13]

Procurement

On 28 June 2016, CDPQ Infra launched two public tenders in parallel: one for "Engineering, Procurement and Construction" (EPC, or "Ingénierie, Approvisionnement et Construction des infrastructures" (IAC) in French), and a second, for "Rolling Stock, Systems and Operation and Maintenance Services" (RSSOM, or "Fourniture du Matériel Roulant, de Systèmes de conduite automatique et de Services d'Exploitation et de Maintenance" (MRSEM) in French).[14][15] Following a prequalification phase, the Caisse's subsidiary announced, on 10 November 2016, the qualified candidates that would be allowed to submit a bid:

According to LaPresse, final bids were submitted to CDPQ Infra on 27 October 2017.[18] On 10 November 2017, the date of the planned announcement of the selected contractors, the procurement process was "postponed indefinitely" to provide more time for analysis and evaluation of the bids received.[19] On 8 February 2018, CDPQ Infra finally announced its selection: Groupe NouvLR consortium for the EPC contract (SNC-Lavalin Grands Projets, Dragados, Aecon, Pomerleau, EBC and AECOM) and the Groupe des Partenaires pour la Mobilité des Montréalais for the RSSOM contract (Alstom and SNC-Lavalin O&M).[17][20] The contracts' value is estimated to be around $6.3 billion, of which approximately 80% is for the EPC contract.[21]

Construction

Preparatory work began in late March 2018.[22] On 12 April 2018, the project broke ground officially.[23]

In December 2019, CDPQ revised the capital cost of the project to $6.5 billion, an increase of $230 million.[24][25]

In November 2020, a disruption from an "unexpected" explosion during the renovation of the Mont Royal Tunnel, likely caused by century-old explosives, delayed the opening of the central section of the REM from 2022 to 2023.[26]

In June 2021, CDPQ updated the project costs to $6.9 billion, an increase of $350 million, citing impacts from the COVID-19 pandemic in Montreal.[27][4] In June 2022, CDPQ Infra acknowledged that construction issues with the Mount Royal Tunnel,[28] labour shortages and material supply issues would postpone the opening of most REM stations to 2024. The delay had also resulted in higher costs for the project overall, exceeding the last projected budget estimate of $6.9 billion.[29] No new estimate of the project cost was provided.

Route

The primary route follows the Mount Royal Tunnel, where new underground stations are being built to connect with the existing McGill and Édouard-Montpetit Metro stations. A new connection to the Mascouche commuter rail line will be built near the A-40 at the Côte-de-Liesse station to allow this line that previously used the tunnel to have access to downtown.

Southeast from Central Station, the line will follow existing rail lines until Marc-Cantin Street, where it will transition to an elevated guideway and cross to Nuns' Island, and then use a rail deck constructed on the new Champlain Bridge to cross the St. Lawrence River. Three stations in Brossard on the South Shore are being built: Panama, connecting to the existing bus terminal; Du Quartier, directly connected to the DIX30 commercial district; and Brossard, a future bus terminus.

The northwest branch will be a direct conversion of the existing Deux-Montagnes line, with a doubling of the tracks beyond Bois-Franc station. On the West Island, a new airport branch will separate near the A-13, with a stop in Technoparc Saint-Laurent before terminating at Montréal–Pierre Elliott Trudeau International Airport. The other branch will follow an existing freight rail spur through Pointe-Claire, then follow the Quebec A-40 alignment just east of St-Jean Boulevard and continue through Kirkland before ending in Sainte-Anne-de-Bellevue.

In the city centre, three stations are being built to connect with existing Metro lines: McGill will connect with the Green Line,[11] Édouard-Montpetit will connect with the Blue Line,[11] and Bonaventure Gare Centrale will connect with the Orange Line.

REM system and stations with their originally proposed names

Rolling stock

  • Montreal REM
  • (Saint-Laurent model)
[30]
REM rolling stock preview - exterior.jpg
REM rolling stock preview - interior.jpg
ManufacturerAlstom
Family nameMetropolis
Constructed2020
Number built212 carriages (106 units)
Formation2-car units, 1–2 units per train
Capacity300 per 2-car unit
Specifications
Train length38.1 m (125 ft 0 in) per unit
Car length19.05 m (62 ft 6 in) over coupler faces
Width2.94 m (9 ft 7+34 in)
Height3.9 m (12 ft 9+12 in) (excluding pantograph)
Doors3 per side per car
Wheelbase
  • Bogie: 2,300 mm (7 ft 6+12 in)
  • 14,910 mm (48 ft 11 in) (between outer axles)
Maximum speed100 km/h (62 mph)
Weight232 t (228 long tons; 256 short tons), 2 units
Axle load14.5 t (14.3 long tons; 16.0 short tons)
Traction motors4 × 185 kW (248 hp) each
Power output
  • 740 kW (990 hp) per car
  • 1,480 kW (1,980 hp) per unit
Electric system(s)Overhead line1,500 V DC
Current collector(s)Pantograph
UIC classificationBo′Bo′+Bo′Bo′ (one unit)
Braking system(s)Air
Safety system(s)Fully automated (GoA4)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Notes/references
[31]

The REM uses 106 Alstom Metropolis trains arranged in two-car sets for a total of 212 cars. At rush hour, trains will be paired together in four-car sets.[30] The external livery is white, grey, and bright green, matching the REM logo. The trains are fully automated with no driver cabs within the cars.[32] Each pair of cars has a capacity of approximately 300 people.

Stations

The REM will consist of 26 stations on three branches. Twelve of these stations are on the former suburban Deux-Montagnes line and will become part of the REM after being converted to rapid transit standards. Several have received new names since the project's inception.[33]

South Shore and Central section (all branches)

All stations on the main branch of the Réseau express métropolitain are projected to have a train frequency of 2.5 minutes during rush hour and every 5 minutes otherwise, both towards Brossard station and towards the three different branches.

Station Opening for REM[34] Opened Parking spots[33] Bike racks Connections
Brossard Q2 2023 N/A 2950 50 RTL, Exo; 22 bus platforms
Du Quartier Q2 2023 None 74 RTL; street stops only
Panama Q2 2023 700 200 Terminus Brossard-Panama; RTL and Exo; 31 bus platforms
Île-des-Soeurs Q2 2023 None 20 STM; 4 bus platforms
Griffintown–Bernard-Landry 2023 None None STM; street stops only
Central Station Q2 2023 1943 None None VIA Rail Canada simplified.svg, AmtrakAmtrak, AMT Mont-Saint-Hilaire icon.png Mont-Saint-Hilaire line, MtlMetro2.svg Bonaventure
Downtown Terminus (Terminus RTL), Société de transport de Montréal (STM)[35]
Several other nearby connections via the RÉSO underground city.
McGill Q4 2024 1966 None None MtlMetro1.svg McGill, STM
Several other nearby connections via the RÉSO underground city.
Édouard-Montpetit Q4 2024 1988 None 30 MtlMetro5.svg Édouard-Montpetit, STM
Canora Q4 2024 1918 None 100 STM; street stops only
Ville-de-Mont-Royal Q4 2024 1918 None 60 STM; street stops only
Côte-de-Liesse Q4 2024 N/A None 35 AMT Mascouche icon.png Mascouche line; STM; street stops only
Montpellier Q4 2024 1918 None 60 STM; street stops only
Du Ruisseau Q4 2024 1994 1,060 45 STM, STL; street stops only. In the future, 1 bus platform and street stops
Bois-Franc Q4 2024 1994 740 120 STM, STL; street stops only. In the future, 6 bus platforms and street stops

Deux-Montagnes branch

Stations on the Deux-Montagnes branch are projected to run every five minutes during rush hour, and every fifteen minutes otherwise.

Station Opening for REM[34] Opened Parking spots Bike racks Connections
Sunnybrooke Q4 2024 1994 400 40 STM; street stops only
Pierrefonds-Roxboro Q4 2024 1944 1,140 80 STM; 6 bus platforms and street stops
Île-Bigras Q4 2024 1995 45 20 STL (taxibus T26 only),[36]
Sainte-Dorothée Q4 2024 1995 975 45 STL; 6 bus platforms
Grand-Moulin Q4 2024 1925[37] 304[38] 44 Exo; street stops only
Deux-Montagnes Q4 2024 1995 1,256[39] 247 Exo; 6 bus platforms and street stops

Anse-à-l'Orme branch

The Anse-à-l'Orme (formerly Sainte-Anne-de-Bellevue) branch of the Réseau express métropolitain is projected to run every ten minutes during rush hour, and every fifteen minutes otherwise.

Station Planned opening[34] Parking spots Bike racks Connections
Des Sources Q4 2024 500 20 STM; 1 bus platform and street stops
Fairview–Pointe-Claire Q4 2024 700 50 STM; 17 bus platforms
Kirkland Q4 2024 2,500 30 STM; 6 bus platforms
Anse-à-l'Orme Q4 2024 200 20 STM, Exo; 11 bus platforms

Airport branch

The Airport branch of the Réseau express métropolitain is projected to run every ten minutes during rush hour and every fifteen minutes otherwise.

Station Planned opening[34][40] Parking spots Bike racks Connections
Marie-Curie 2025 None 20 STM; street stops only
YUL–Montréal–Trudeau Airport 2025 None None Connection to Montréal–Pierre Elliott Trudeau International Airport

Controversies

In a report prepared by the Bureau d'audiences publiques sur l'environnement (BAPE) and released on 20 January 2017, the project was criticized for failing to provide crucial information on the project's financial model, environmental impact, as well as the impact on ridership levels throughout the public transit network across Montreal. Without such information, the BAPE declared that it was "premature to authorize the approval of this project".[41] The BAPE also stated that CDPQ Infra had not met its obligations for transparency, as it had failed to provide information in a timely fashion on the ridership levels of the REM's three branches.[41] The CDPQ Infra was also reproached for not studying the impact of the REM on existing public transit authorities.[41] CDPQ Infra was criticized for not being able to answer questions like how much tickets would cost, whether municipalities on the REM would themselves have to pay for the necessary infrastructure for access to it, and whether municipalities would also have to contribute to the REM's operation.[41]

A lawsuit filed by Coalition Climat further alleged that the REM project violated federalism for a lack of federal assessment of the potential harm to citizens' environmental rights by its potential contribution to noise pollution and urban heat islands. The lawsuit was dismissed by the Quebec Superior Court on 13 December 2017.[42]

Another controversy occurred in November 2019, when Montreal mayor Valerie Plante proposed naming Griffintown's REM station after controversial politician Bernard Landry, sparking a backlash from the city's Irish community.[43] As a compromise, the station was named Griffintown–Bernard-Landry, which still proved controversial.[44]

Future lines, stations, and extensions

On 20 May 2019, the Quebec government announced that it had requested CDPQi to study two REM extensions. One route would be nearly 20 km (12 mi) north to Carrefour Laval and the other nearly 30 km (19 mi) south to Chambly and St-Jean-sur-Richelieu.[45] The government also made a request to determine the best electrified transit system to be put in place for the East Island, with the possibility of it being a new REM line.[45] The proposal became the REM de l'Est Project.

Dorval station

The federal government requested the Canadian Infrastructure Bank study a possible extension of the REM to Dorval Exo train station and to Dorval Via Rail station to connect with Exo and Via Rail trains.[46] This station would be about a 1-kilometre (0.62 mi) extension from the Airport station. The STM bus station is located south of the CP, CN tracks and west of the Via Rail station.

Bridge-Bonaventure station

The city of Montreal requested two stations, instead of one station, at Bassin Peel.[47] The second station would be added between Île-des-Soeurs and Griffintown–Bernard-Landry stations.[48]

REM de l'Est

REM de l'Est
Cégep Marie-Victorin
Montréal-Nord
Pointe-aux-Trembles
AMT Mascouche icon.png
Coture
Rousselière
St-Léonard
Tricentenaire
MtlMetro5.svg
Lacordaire
St-Jean Baptiste
St-Zotique
Contrecoeur
Hôpital Rosemont
Honoré-Beaugrand
MtlMetro1.svg
MtlMetro1.svg
Assomption
Haig
Viauville
St-Clément
Pie-IX Sud
Davidson
Dufresne
Cartier
Labelle
MtlMetro2.svg
St-Urbain
Robert-Bourassa
Réseau express métropolitain logo.png MtlMetro2.svg MtlMetro1.svg AMT Mascouche icon.png

The "REM de l'Est" is a planned second REM line which would be 32 km (20 mi) long. Announced in 2020,[49][50] it would use the existing REM technology but not connect directly to the first section of the network.

Beginning at Robert-Bourassa, the line would run east on an elevated guideway along the banks of the St. Lawrence River until St-Clément, where it would turn north and split into two branches:

The REM de l'Est would add 23 new stations:[51]

Station Branch Connections
Robert-Bourassa Common section Réseau express métropolitain logo.png AMT Mascouche icon.png Central Station MtlMetro1.svg McGill, MtlMetro2.svg Square-Victoria-OACI, local buses
St-Urbain Common section Local buses
Labelle Common section MtlMetro2.svg Champ-de-Mars, local buses
Cartier Common section Local buses
Dufresne Common section Local buses
Davidson Common section Local buses
Pie-IX Sud Common section Pie-IX bus rapid transit, local buses
St-Clément Common section Local buses
Viauville Common section
Assomption Cégep Marie-Victorin MtlMetro1.svg Assomption, local buses
Hôpital Rosemont Cégep Marie-Victorin Local buses
St-Zotique Cégep Marie-Victorin Local buses
Lacordaire Cégep Marie-Victorin MtlMetro5.svg Lacordaire (future), local buses
St-Léonard Cégep Marie-Victorin Local buses
Couture Cégep Marie-Victorin Local buses
Montréal-Nord Cégep Marie-Victorin Local buses
Cégep Marie-Victorin Cégep Marie-Victorin Local buses
Haig Pointe-Aux-Trembles Local buses
Honoré-Beaugrand Pointe-Aux-Trembles MtlMetro1.svg Honoré-Beaugrand, local buses
Contrecoeur Pointe-Aux-Trembles Local buses
St-Jean Baptiste Pointe-Aux-Trembles Local buses
Tricentenaire Pointe-Aux-Trembles Local buses
Rousselière Pointe-Aux-Trembles Local buses
Pointe-Aux-Trembles Pointe-Aux-Trembles AMT Mascouche icon.png Mascouche line, local buses

Lachine "Pink Line West" branch

Mayor Valérie Plante announced funding for the West branch of the "Pink Line".[52] This branch would be a continuation of a REM line, if it is the technology chosen by the CDPQi. If the REM technology is chosen, this branch would connect Lachine to Downtown Montreal as an extension of the REM de L'Est.

See also

References

  1. ^ "Sommaire des previsions d'achalandage du REM" (PDF). www.cdpqinfra.com. CDPQ Infra Inc. February 2017.
  2. ^ "Les trains du REM seront construits en Inde" (in French). 12 April 2018. Retrieved 13 April 2018.
  3. ^ Magder, Jason (22 April 2016). "Electric light-rail train network spearheaded by Caisse de dépôt to span Montreal by 2020". Montreal Gazette. Retrieved 22 April 2016.
  4. ^ a b "REM light rail project price tag rises due to pandemic complications". Montreal. 3 June 2021. Retrieved 5 June 2021.
  5. ^ "Réseau électrique métropolitain". cdpqinfra.com. 10 October 2019. Archived from the original on 2 May 2021. Retrieved 2 May 2021.
  6. ^ "Le REM de la Rive-Sud encore retardé". La Presse (in French). 20 October 2022. Retrieved 21 October 2022.
  7. ^ Magder, Jason. "The Caisse's first two mass transit projects in brief - Montreal Gazette". Montreal Gazette.
  8. ^ Delean, Paul. "Caisse revs up for new role as infrastructure provider". Montreal Gazette.
  9. ^ Briginshaw, David (30 June 2016). "Tendering starts for Montreal rail project". International Railway Journal. Retrieved 5 July 2016.
  10. ^ Magder, Jason (25 November 2016). "Three REM train stations added to proposed route through downtown Montreal". Montreal Gazette. Retrieved 25 November 2016.
  11. ^ a b c Wanek-Libman, Mischa (28 November 2016). "Proposed Montréal REM project grows by three stations and CA$400M". Railway Track & Structures. Simmons-Boardman Publishing Inc.
  12. ^ "The Government of Canada confirms a $1.28-billion investment in the Réseau électrique métropolitain". www.newswire.ca. Retrieved 20 July 2017.
  13. ^ "Citing 'value for money', Caisse extends bidding for REM electric-train project". Montreal Gazette. 1 December 2017. Retrieved 7 January 2018.
  14. ^ "Ingénierie, Approvisionnement et Construction des infrastructures du Réseau Électrique Métropolitain de Montréal" (PDF) (in French). 28 June 2016. Archived from the original (PDF) on 22 August 2016. Retrieved 21 October 2016.
  15. ^ "Fourniture du Matériel Roulant, de Systèmes et de Services d'Exploitation et de Maintenance du Réseau Électrique Métropolitain de Montréal" (PDF) (in French). 28 June 2016. Archived from the original (PDF) on 23 August 2016. Retrieved 21 October 2016.
  16. ^ a b c "Appel de qualification : résultats" (PDF) (in French). 10 November 2016. Archived from the original (PDF) on 12 November 2016. Retrieved 11 November 2016.;
  17. ^ a b "Main partners". REM.info. Retrieved 1 March 2018.
  18. ^ "REM: les offres finales des soumissionnaires déposées aujourd'hui" (in French). 27 October 2017. Retrieved 30 October 2017.
  19. ^ "REM: le choix des consortiums reporté". 11 November 2017. Retrieved 27 November 2017.
  20. ^ "REM: les offres finales des soumissionnaires déposées aujourd'hui" (in French). 8 February 2018. Retrieved 8 February 2018.
  21. ^ "CDPQ Infra awards contracts for Montreal REM". 8 February 2018. Retrieved 9 February 2018.
  22. ^ "South Shore preparatory work gets underway | REM". rem.info.
  23. ^ "Construction of the Réseau express métropolitain has officially started". CDPQ. 12 April 2018. Retrieved 8 October 2022.
  24. ^ "Montreal REM cost revised up to $6.5 billion - constructconnect.com". Daily Commercial News. 9 January 2020. Retrieved 5 June 2021.
  25. ^ Boshra, Basem (17 December 2019). "Closing of Mount Royal Tunnel postponed, cost of REM project jumps by $230 million". Montreal. Retrieved 5 June 2021.
  26. ^ "Opening of REM delayed after COVID-19 work stoppages and an 'unexpected' explosion". Canadian Broadcasting Corporation. 11 November 2020.
  27. ^ "REM construction moving forward in Greater Montreal but problems remain". Global News. Retrieved 5 June 2021.
  28. ^ "Century-old Mount Royal tunnel gets shored up for REM's McGill station". montrealgazette. Retrieved 22 June 2022.
  29. ^ "Tunnel problems and labour shortage delay opening of most REM stations". montrealgazette. Retrieved 22 June 2022.
  30. ^ a b "Five things to keep in mind regarding REM cars | REM". rem.info. 16 November 2020. Retrieved 8 October 2022.
  31. ^ "Rolling stock". REM. Retrieved 8 October 2022.
  32. ^ "Alstom Presents Its Metropolis Vehicle for the Montréal REM". Railway-News. 1 April 2019. Retrieved 8 October 2022.
  33. ^ a b "Stations". REM. Réseau express métropolitain. Retrieved 13 February 2020.
  34. ^ a b c d "Commissioning schedule". Réseau express métropolitain. January 2022. Retrieved 7 February 2022.
  35. ^ "Maps". stm.info. Retrieved 20 July 2017.
  36. ^ T26
  37. ^ "Transit History of the Banlieues de Montreal, Quebec". Retrieved 8 February 2018.
  38. ^ "Gare Grand-Moulin". RTM.
  39. ^ RTM. "Gare Deux-Montagnes".
  40. ^ Tomesco, Frédéric (20 May 2022). "Opening of REM's airport section delayed until at least 2025". Montreal Gazette. Retrieved 24 May 2022.
  41. ^ a b c d "Train électrique: un projet prématuré, selon le BAPE - Bruno Bisson - Montréal". lapresse.ca. 21 January 2017. Retrieved 20 July 2017.
  42. ^ "Challenge of Caisse de dépôt's REM train project rejected by Superior Court". montrealgazette.ca. 13 December 2017. Retrieved 1 January 2018.
  43. ^ "OTL Blog » Blog Archive » An Open Letter from a City of Montreal Ambassador to Mayor Valerie Plante RE: Griffintown REM Proposal and Negative International Reaction". Retrieved 14 February 2020.
  44. ^ Luft, Amy (22 June 2020). "Montreal's Irish community disappointed new REM station in Griffintown will be named after former premier Bernard Landry". Montreal.
  45. ^ a b "Plante fumes as Quebec considers possible expansion of REM | Montreal Gazette". 7 May 2019.
  46. ^ "Un prolongement du REM pourrait relier la gare de Dorval à l'aéroport". Le Devoir. 19 July 2019.
  47. ^ "Bassin Peel: la Ville demande deux stations du REM". La Presse. 31 October 2019.
  48. ^ "Montréal veut une station du REM dans Bridge-Bonaventure". 2 June 2022. Retrieved 24 August 2022.
  49. ^ Teisceira-Lessard, Philippe; Ouellette-Vézina, Henri (15 December 2020). "Un train toutes les deux minutes pour le nord et l'est de Montréal" [A train every two minutes for north and east of Montreal]. La Presse (in French). Retrieved 15 December 2020.
  50. ^ Olson, Issac (15 December 2020). "Montreal's east end to get its own $10B light-rail network". CBC News. Retrieved 15 December 2020.
  51. ^ "Discover REM de l'Est". 12 December 2020.
  52. ^ Page, Julia; McKenna, Kate (26 June 2019). "Montreal secures Quebec support for part of Pink line — a tramway from downtown to Lachine". CBC News Montreal. Retrieved 15 December 2020.

External links