Kuril Flyover

From Justapedia, unleashing the power of collective wisdom
Jump to navigation Jump to search
Kuril Flyover
LocaleDhaka
Official nameKuril Flyover
Characteristics
Total length3.1 km
History
Constructed byProject Builders Limited, China Major Bridge Engineering Corporation
Construction start2 May 2010
Construction end4 August 2013
Construction cost3.06 billion taka[1]

The Kuril Flyover is the third largest flyover in Bangladesh. Its foundation stone was laid on 2 May 2010.[1][2][3] Finally the work started in March 2011.[4]

The flyover was opened on 4 August 2013.[1]

References

  1. ^ a b c "PM opens Kuril Flyover". bdnews24.com. Retrieved 10 December 2020.
  2. ^ "PM inaugurates Kuril flyover". The Daily Star. Retrieved 10 December 2020.
  3. ^ "PM to open Kuril Flyover on Sunday". Dhaka Tribune. Retrieved 10 December 2020.
  4. ^ "Kuril flyover open for public". Risingbd.com. Retrieved 10 December 2020.